5881EN: UL Commercial Fire Installation

For UL864 Commercial Fire Installations, you will need to purchase separately the “5800BOX” (in which the circuit board will be installed). Follow the instructions below and refer to Figure 3.

1. Mount the rear half of the 5800BOX directly to the wall in the selected location, hinged side up. Secure using the 4 screws provided and insert screw in tamper tab, refer to Installation, step 3c and Fig. 2.

2. Thread the ECP wire through the conduit and feed through the opening at the side of the box rear.

3. Remove the circuit board from the 5881EN case and discard case. Install the circuit board into the 5800BOX and secure using the 4 screws provided.

4. Connect the ECP terminals as shown.

5. Insert slots on top of box cover into hinges on top of box back and secure using 2 cover securing screws.

NOTE: For UL-864 Fire installations, ECP Isolator (PN ECP-ISO) is required.